The Create Baseline: Single Baseline section is shown.
At the top right are the Cancel, Back, and Finish buttons.
The Baseline Name field is empty.
In the Baseline Interval section, the Snapshot Range option is selected.
The Change Chart Time Period navigation tree is collapsed.
In the Select Time Period section, the Period Start Time option shows Feb 7, 2012 11:50:20 AM CST. The option is selected. The Period End Time option shows Feb 7, 2012 12:00:22 PM CST. This option is not selected.
A chart shows active sessions on the y-axis. The values range from 0 to 3.410. The x-axis shows hours of day, shown in 2-hour intervals, ranging from 1:00 p.m. Feb 6, 2012 to 12:00 p.m. Feb 7, 2012.
The Time Range option is not selected.
The Start Time is Feb 8, 2012 at 12:00 p.m. The End Time is Feb 8, 2012 at 12:25 p.m.